The Malian government has officially approved the final financing stage for the 225 kV North Bamako High Voltage Loop (PBNB) project. With a total investment of €166 million, this initiative is set to become the backbone of electricity supply for the capital and its surrounding areas. The project, highlighted by the African Development Bank, aims to connect 10,000 new households and small businesses while significantly enhancing power quality for over 40 industrial units.
Project components and infrastructure
The PBNB involves constructing a 103-kilometer double-circuit 225 kV transmission line linking key locations such as Kodialani, Kambila, Safo, and Dialakorobougou. Additionally, the initiative includes expanding two existing substations and erecting three new transformation stations, with major hubs planned for Safo and Kénié.
Funding milestones and financial structure
Operational progress accelerated in early July when the National Transitional Council (CNT) of Mali ratified loan agreements signed between the African Development Bank and the Malian government on February 25, 2026. This approval follows earlier financial commitments, including a €68 million loan from the Islamic Development Bank in December 2025, a €43.7 million pledge from the West African Development Bank in May 2025, and an initial €45 million investment from the European Investment Bank in December 2020.
The African Development Bank’s €30.8 million loan from its concessional lending arm, the African Development Fund, forms the core of its contribution. Supporting this are the Transition Support Facility’s €16.6 million loan, a €4.4 million loan and €5.9 million grant from the Climate Investment Fund, and an additional €1.9 million grant from the Green Climate Fund. These combined resources cover 36.13% of the total project cost, with the Malian government contributing an additional 3.6% through co-financing.
Long-term energy resilience
Once completed, the infrastructure will not only meet immediate demand but also lay the groundwork for future energy integration. The project will seamlessly align with upcoming power sources, including the Guinea-Mali interconnection, the Manantali 2 transmission line, and solar energy plants planned for Kambila and Safo.